Ampurius Nu Homes Holdings Ltd v Telford Homes (Creekside) Ltd (2012) EWHC 1820
[edit] High Court (Chancery Division) (England and Wales) 2012
The claimant and the defendant (a construction company) entered into a contract for the construction and grant of long leases on a development scheme for which the defendant acquired the freehold. The defendant was required under the contract to proceed with 'due diligence' and to 'use reasonable endeavours' to complete the works by the target date. However, the defendant ran into financial difficulties ceased work.
The claimant alleged that this was a repudiatory breach, but did not terminate the contract for 11 months. It was the defendant who repudiated the contract.
Judgment was given in favour of the claimant.
In so doing, The court held that the defendant was in breach of the term of the contract requiring due diligence by failing to carry out the works assiduously or expeditiously. It was also held that although the breach may not have been repudiatory at the outset, it could become so over time if it deprived the innocent party of the benefit of a significant part of the contract. Negotiation over the course of the breach did not mean the claimant had affirmed the contract.
[edit] Court of Appeal (Civil Division) (England and Wales) 2013
In 2013 this decision was overturned by the Court of Appeal. It was not disputed that Telford had been in breach of contract, but the court held that an 18 month delay on a 999-year lease was not sufficient to constitute a repudiatory breach (a breach that it indicates one party no longer intends to accept its obligations under the contract, allowing the innocent party to terminate the contract and to sue for damages) and so did not entitle Ampurius to terminate the contract.
[edit] External references
Featured articles and news
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherit assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.

















